Bone Student Center
 

Action 24C

Construct a new north face for Bone Student Center/Braden Auditorium.

 

Baseline Information

  • A new north face for Bone Student Center/Braden Auditorium will visually connect it to the new North Quad.

Action Steps

Progress will be measured based upon the completion of the following action steps.

Color codes for this plan's phases
Blue bullets represent the Constuction Phase. Planning
Red bullets represent the Constuction Phase. Design
Green bullets represent the Constuction Phase. Construction
  1. Action Step 01:  Review previous design studies for expanding Bone Student Center. Identify any factors that should be considered as part of this planning effort.

  2. Action Step 02:  Engage design consultants to prepare conceptual studies for expanding Bone Student Center and constructing a new north face for the building.

  3. Action Step 03:  Share results with the Capital Planning and Budget Team.

  4. Action Step 04:  Share results with the President’s Cabinet.

  5. Action Step 05:  Get approval for the project.

  6. Action Step 06:  Advertise for and select architectural consultants for design of project.

  7. Action Step 07:  Begin design.

  8. Action Step 08:  Complete schematic design (25%).

  9. Action Step 09:  Complete design development (50%).

  10. Action Step 10:  Complete construction documents (75%).

  11. Action Step 11:  Bid the project.

  12. Action Step 12:  Award the project.

  13. Action Step 13:  Mobilize and begin construction.

  14. Action Step 14:  Track construction through web site updates.

  15. Action Step 15:  Complete construction.

  16. Action Step 16:  Move in.

Scale begins at 0% minimum. 12% completed Scale ends at 100% maximum.
 

News and Updates

News and Updates Archive

There is no news items about this action. Please visit the news archive for articles about other actions.