Action 04A

Reconfigure classrooms and offices in Schroeder Hall.

 

Baseline Information

  • Located at the corner of College Avenue and University Street, Schroeder Hall contains 60,119 net assignable square feet which houses 42 classrooms with a total capacity for 2,383 students. Illinois State University received $18.7 million from the state for the overall renovation of the building.

    Please visit www.schroeder.ilstu.edu for further details of the project.

Action Steps

Progress will be measured based upon the completion of the following action steps.

Color codes for this plan's phases
Blue bullets represent the Constuction Phase. Planning
Red bullets represent the Constuction Phase. Design
Green bullets represent the Constuction Phase. Construction
  1. Action Step 01:  Complete design development phase drawings.

  2. Action Step 02:  Complete review of 50 percent documents, including plans and specifications.

  3. Action Step 03:  Complete review of 95 percent documents, including plans and specifications.

  4. Action Step 04:  Complete construction documents.

  5. Action Step 05:  Establish bid dates for construction.

  6. Action Step 06:  Complete renovations in Milner, Ropp and Turner to house Schroeder programs during the renovation.

  7. Action Step 07:  Relocate faculty, staff and classes to interim locations.

  8. Action Step 08:  Award construction contracts through the Capital Development Board.

  9. Action Step 09:  Demolish temporary structure (Faculty Office Building, also known as Butler Hall).

  10. Action Step 10:  Complete Utility Work.

  11. Action Step 11:  Initiate East Wing construction.

  12. Action Step 12:  Complete East Wing construction.

  13. Action Step 13:  Move faculty into completed East Schroeder offices.

  14. Action Step 14:  Begin West Wing construction.

  15. Action Step 15:  Complete West Wing construction, move faculty, offices and classes into permanent location within Schroeder Hall.

  16. Action Step 16:  Dedicate renovated building and celebrate project completion.

Scale begins at 0% minimum. 62% completed Scale ends at 100% maximum.
 

Accomplishments

The following action steps have been completed or are in progress:

  1. Action Step 01: Completed 

  2. Action Step 02: Completed 

  3. Action Step 03: Completed 

  4. Action Step 04: Completed 

  5. Action Step 05: Completed 

  6. Action Step 06:  Milner reported finished 2/18/04.

  7. Action Step 07: Completed 

  8. Action Step 08: Completed 

  9. Action Step 09:  Butler Hall reported demolished in January 2004.

  10. Action Step 11:  General contractor began working on 3rd and 4th floors of Schroeder East in March, 2004.

 