Vrooman Dining Center
 

Action 42A

Renovate Vrooman Dining Center.

 

Baseline Information

  • Vrooman Dining Center is located between Hewett and Manchester Residence Halls at the corner of College Avenue and Fell Avenue. Vrooman has 36,826 net assignable square feet.

    Vrooman is an all-you-eat style dining center including: Bev’s Deli, Donzello’s pizza, a huge salad bar, traditional fare, stir fry, and daily selections from the grill. Additional choices include The Earth’s Palette (vegetarian cuisine dishes) and The Parrot’s Echo (casual dining restaurant with a tropical atmosphere).

Action Steps

Progress will be measured based upon the completion of the following action steps.

Color codes for this plan's phases
Blue bullets represent the Constuction Phase. Planning
Red bullets represent the Constuction Phase. Design
Green bullets represent the Constuction Phase. Construction
  1. Action Step 01:  Review the physical improvements identified in the Residential Long Range Improvement Plan.

  2. Action Step 02:  Meet with Campus Dining Center administrators to discuss possible approaches for developing a project or projects that will result in an improved environment for Vrooman.

  3. Action Step 03:  Identify the best approach, including timing, proper sequence of work and possible source of funds.

  4. Action Step 04:  Present the recommended plan to the Capital Planning and Budget Team.

  5. Action Step 05:  Get approval for the project.

  6. Action Step 06:  Advertise for and select architectural consultants for design of project.

  7. Action Step 07:  Begin design.

  8. Action Step 08:  Complete schematic design (25%).

  9. Action Step 09:  Complete design development (50%).

  10. Action Step 10:  Complete construction documents (75%).

  11. Action Step 11:  Bid the project.

  12. Action Step 12:  Award the project.

  13. Action Step 13:  Mobilize and begin construction.

  14. Action Step 14:  Track construction through web site updates.

  15. Action Step 15:  Complete construction.

  16. Action Step 16:  Open up.

Scale begins at 0% minimum. 0% completed Scale ends at 100% maximum.
 